Amethyst
About the project
Our first battery storage project in Zuid Holland, the Netherlands, boasts a 45 MW capacity with a 2-hour duration. Through collaboration with local authorities and innovative modular designs, we optimized space utilization and streamlined the permitting process. Grid connection is established, and the project is on track for completion by early 2026, positioning it as a key contributor to regional energy stability.
Installed Capacity
45 MW
Duration
2hrs
Location
Zuid Holland (NL)
Grid
Applied
Land
Secured
Permit
Granted
COD
Early 2026
1 / 4
An exterior view of the battery park site.
Project Overview
Construction is set to commence in the fall of 2024.
Battery
The battery, consisting of 144 Fluence cubes, has a capacity of 90MWh and will on average store enough energy supply equivalent for 21,500 households per day.
Location
Utility-scale BESS is being constructed in the port area of Dordrecht, on a 6000m² site, x distance from the Dordrecht substation.
Congestion
Our market access partner will optimize the battery to maintain this balance without increasing local congestion.
Partners
Equity
- Macquarie Capital
- EPICo² Fund
Debt finance
- ABN AMRO Bank N.V.
Market access
- Eneco
BESS supplier
- Fluence
Balance of Plant
- Equans
Owners engineer
- Ventolines
Market forecast
- EnAppSys
DSO
- Stedin