Our Projects

Solar and wind energy create increasing imbalance risks and congestion problems. We are currently developing multiple locations for utility-scale battery energy storage systems, both in congested and non-congested locations. Each of these systems has a power capacity between 20MW and 400MW and can be charged and discharged for multiple hours. These strategically located battery systems help balancing the energy grid and enable the energy transition.

Non-congestion locations

Non-congested locations have the maximum level of flexibility in time and capacity for the energy suppliers to operate the battery.

Congestion locations

In congested locations special agreements are made with the grid operator to help manage congestion. The energy supplier operates the battery in close collaboration with grid operator for optimal results.

Project Amethyst
Project Haematite
Project Tiger Eye
Project Labradorite
Project Tiger Eye
  • Installed Capacity: 32 MW

  • Duration: 2hrs

  • Location: Leudal (NL)

  • Grid: Applied

  • Land:  Secured

  • Permit: Granted

  • Targeted COD: Early 2025

 

Project Amethyst
  • Installed Capacity: 45 MW

  • Duration: 2hrs

  • Location: Dordrecht (NL)

  • Grid: Applied

  • Land:  Secured

  • Permit: Granted

  • Targeted COD: Early 2025

 

Project Haematite
  • Installed Capacity: 40 MW

  • Duration: 2hrs

  • Location: Zoetemeer (NL)

  • Grid: Applied

  • Land:  Secured

  • Permit: In process

  • Targeted COD:  2025

Project Labradorite
  • Installed Capacity: 20 MW

  • Duration: 2hrs

  • Location: Leeuwarden (NL)

  • Grid: Applied

  • Land:  Secured

  • Permit: in process

  • Targeted COD: 2025